Baystate Medical Center (BMC) Construction

Construction continues on the BMC 'Hospital of the Future', with a scheduled completion date of early 2012. Check here for the latest news, construction schedule and advisories related to the construction of the new facility.
Construction Advisory
March 6, 2011 - Exterior masonry and ornamental roofing components are complete on the building's facade. Interior work continues on schedule. Road work near the hospital continues under the direction of the Springfield Water & Sewer Commission and the Springfield DPW. Underground construction in this area is nearly complete. This work is not directly related to the construction of the hospital, but impacts the traffic in the nearby district.
Construction Schedule
November 2010 - April 2011
The exterior facade of the building contintutes take shape, with the completion of construction of the brick and stone components. The building will begin to take on its true 'distinction' as this work progresses. Installation of glass and window are expected to be completed during construction period.
Expect traffic to be busy at the construction site throughout this period as the delivery of construction materials and project components continues, and water and sewer work continues.
Video Tour of the Hospital of the Future
Click Here to take the tour
'Hospital of the Future' Official Website
Click Here to visit the site
Progress Pictures
November 2010
November 2010
November 2010
March 2010
October 2009
October 2009
October 2008